Temporary Construction Power in Texas: From Temp Meter to Permanent Service
How temporary construction power works in Texas: ESI IDs, TDU and REP steps, contract terms, and the handoff to a permanent meter.

Before a building has a permanent electric meter, it often has a temporary one. A construction trailer needs power. So do saws, compressors, welders, site lighting and, eventually, the first wave of electricians and HVAC crews. In Texas, that temporary service has its own account, its own identifier and its own contract, and it has to be handed off cleanly to a permanent meter when the building is ready. If the handoff slips, the opening date slips with it.
This guide explains temporary construction power in Texas: how a temporary meter is set up, who you deal with at each step, why the retail contract for a short-lived account deserves more attention than it usually gets, and how to move from temporary service to a permanent meter without a gap. It's written for general contractors, developers, builders and owners who are building a new facility, and it focuses on the construction phase. If you're enrolling a permanent meter for an existing or finished building, our guide to adding an electricity meter for a Texas business is the better starting point.
A note on sources: the process details below come from published Oncor Electric Delivery new-construction materials, since Oncor serves a large part of the state. Each of Texas's delivery utilities (CenterPoint Energy, AEP Texas, TNMP and others) runs its own procedures and forms, and requirements change. Treat what follows as a map of the general sequence, and confirm the current steps and lead times with your own delivery utility before you plan a schedule around them.
The Texas electricity market splits the job of getting power to a site among different parties, and it helps to know which one you need at each step.
The transmission and distribution utility (TDU), such as Oncor, CenterPoint, AEP Texas or TNMP, owns the poles, wires, transformers and meters in its territory. It designs and builds the connection, sets the meter and assigns the ESI ID, which is the identifier ERCOT and every retailer uses to track a point of delivery. If the project needs new poles, wire or transformers, the TDU assigns a project manager to work with you.
The city or county inspector approves the electrical installation on your side of the meter. In Oncor's process, a confirmed city inspection has to be communicated to Oncor before the meter can be set. In areas where city inspections aren't required, the meter base installation still has to follow the utility's service guidelines.
The retail electric provider (REP) sells you the electricity. You choose it, you sign a contract with it, and it submits the request for the meter to be energized. The retail side is the part of the process that's competitive, which is where we come in. If you're unfamiliar with how the pieces divide, our explainer on TDSP charges on a commercial bill shows how delivery and retail charges fit together on a bill.
The exact steps depend on your utility and your project, but the pattern in Oncor's published materials looks like this.
For a commercial or industrial project, you start new service through the utility's contact center or its online "start new service" request. A project manager is assigned and will ask for basic project information that helps the utility determine the size of the facilities it needs to provide.
Oncor's materials describe obtaining an ESI ID (a premise number) for the temporary pole and a separate one for the permanent meter. A builder request form even includes a line acknowledging that you need an ID for each temporary power pole and for each permanent meter, and that the request does not serve as a meter set request. The utility's customer requirements form for commercial and industrial service has fields for both a temporary and a permanent premise number, and it asks you to say when you need each.
In plain terms: ask for both numbers early, and don't treat the ID as the finish line. It identifies the point of delivery. It doesn't mean a meter is on the way.
For larger projects, expect to provide a site plan showing the proposed transformer, meter and other utility equipment locations, along with electrical load information for the permanent service. Oncor's checklist describes an on-site meeting led by the project manager to review plans and schedule and discuss options for temporary and permanent service. The utility's engineer then designs the system to serve both, and the utility states that it will provide the least-cost design. If the project needs utility construction, a signed service agreement is required before the utility can schedule a crew, and a contribution in aid of construction (CIAC), if one applies, is payable before construction is scheduled. Your estimate and your cost depend on the project, so we can't give you a figure.
The temporary pole or service structure is installed to the utility's specifications. Civil work that you install, such as conduit or trenching, may need to be inspected by the utility's inspector and follow its construction specifications.
Once the electrical work passes inspection, the city communicates the confirmed inspection to the utility, and you apply for service with the REP you've chosen. Oncor's process says that once both the inspection and the application for service have been received, it schedules the work to set the meter. Its toolkit for home builders also notes that if a request is rejected and you can't correct the problem right away, the request has to be made again through the REP. A missed inspection or an incomplete application is the most common way a schedule slips.
This is the part most construction teams treat as an afterthought, and where we can add the most value. Because the temporary account looks small, the contract tends to be whatever the first provider offers. A few things are worth asking about before you agree.
We can't promise that every provider offers short-term or flexible terms on temporary service, because those offerings change. What we can do is ask for them in writing across several providers, which is easier than calling each one yourself.
If you build repeatedly, whether you're a general contractor with several jobs open at once or a developer opening a number of sites a year, then temporary power is a recurring cost and a recurring headache. Each project needs a new temporary ESI ID, a new account and a new closing process, and the same questions come up each time.
A portfolio approach can help:
This is the same thinking behind aggregating accounts on the permanent side. Our guide to electricity procurement for franchise and multi-location businesses explains how combining many sites into one process changes what providers offer, and the same approach can apply to a pipeline of new builds.
The handoff is where projects most often lose days. Oncor's checklist describes the conditions for energizing permanent service in terms that sound simple: meter sockets installed to the utility's metering specifications, all construction associated with the meter socket completed, the permanent ESI IDs in hand, and the customer's application for service ("move-in order") submitted to the REP. Oncor's page for new service adds that meters are installed based on the date you select to start service with your chosen provider.
Here's a hypothetical sequence for a new retail building, to show how the pieces fit together. A builder gets a temporary ESI ID and a permanent ESI ID at the start of the project. The temporary pole goes in, passes inspection and gets a meter, and the contractor works for several months on temporary power. As the building nears completion, the permanent service is inspected, the owner or tenant selects a retail provider and submits the move-in request with the permanent ESI ID, and the utility sets the permanent meter. Finally, the contractor asks the temporary account's REP to remove the meter and service from the temporary pole, and the last bill is settled. At each step, the dates need to line up: if the owner hasn't chosen a provider by the time the building passes inspection, the meter can't be energized on time.
This guide stops at the handoff. Once the permanent meter exists, the story shifts to rates, contract terms and ongoing management, which we cover in other posts. If you're also working through how to enroll or add a permanent meter, see our page on adding a new electricity meter in Texas. For the contract you'll sign on the permanent account, our guides on fixed, variable and indexed plan types and switching commercial electricity providers will help you decide what to ask for. To learn how a competitive bidding process works, see our reverse auction explainer, and for the economics of working with a broker, read how a commercial energy broker gets paid.
Yes. Oncor's published materials describe a separate premise number for the temporary pole and for each permanent meter. A request for the ID is not a request to set the meter.
It depends on your utility and the scope of the work. Oncor's commercial and industrial requirements form asks you to allow up to 10 business days for a preliminary cost estimate and at least three more weeks for scheduling a crew. Simple requests may move faster, but plan for the longer figure and confirm with your utility.
Whoever is the customer of record on the temporary account pays the bill. That's usually the general contractor or the owner, depending on the contract. Decide it in writing before the account is opened.
In competitive areas of Texas, generally yes. You select a REP and sign a contract, just as you would for a permanent account. Ask each provider about short terms, fees and closing procedures.
You (or the contractor) ask the REP on the temporary account to have the meter and service removed from the temporary pole, and the permanent meter is set under a separate account and ESI ID.
The general sequence is similar, with a TDU, an inspection and a retail provider, but forms, lead times and fees differ by utility. Check your utility's current new-construction instructions before you plan a schedule.
Yes, with the retail side. We can collect offers from several providers for the temporary and permanent accounts and help you compare terms. We can't speed up utility construction, inspections or crew scheduling, which stay with the utility and the city.
If you're building a new facility in Texas, or you manage a pipeline of projects, we can help you line up providers for both the temporary and permanent accounts, at no cost to you, since the winning provider pays the broker. Send us your project details through our contact page or call (737) 295-9735. EnergyBrokerTX is a PUC-licensed broker, License #BR260054. For official procedures, always check with your own delivery utility, for example the new-construction section of Oncor's website if you build in Oncor territory.
Submit your account and we'll run a competitive auction with 25+ licensed Texas providers — full bid transparency, no pre-filtering, no obligation.
Get My Free Competing Bids →